Wednesday, 1 March 2017

A NEW LOOK OF KRS DAM



KRS REALITY CHECK – 1
Taking advantage of the rapidly depleting water level at the Krishna Raja Sagar (KRS) Dam, the State Government has launched a series of works to repair and rejuvenate the structure. Works are on to strengthen the walls, plugging leaks and cementing cracks.
Engineers inspecting progress in works

The works are being taken up by the Water Resources Department and Cauvery Neeravari Nigam (CNN) Limited under the project “Dam Rehabilitation and Improvement Project” funded by the World Bank. The total cost of the project is estimated to be Rs. 38.70 crore.

A detailed inspection of the 100-year-old dam has been done and holes on the structure have been identified through “Poly Ironite Ceramic Cementitious Pointing” and they will be filled using Crystalline Technology through Fibre Short Crate. The process will be videographed for precision and the holes will be sealed through grating process. According to officials, the sealing of holes will strengthen the dam which has not seen repairs since decades.
Completed work on inner portion of KRS Dam

Added to this, workers are scaling the dam structure with carriages suspended from the top to check cracks. They are drilling the structure every four metres to test for cracks and leakages. The structure is being scanned through high-powered video cameras and engineers are monitoring the works through the videos.

In the second stage of the project, the 136 floodgates of the reservoir will be replaced at an estimated cost of Rs. 38 crore and the project is in tender stage. Later, the instrumentation works of the dam will be taken up at a cost of Rs. 1.5 crore. “A proposal for other works including rejoining wall and electrification has been sent to the Government and the total estimate is Rs. 30 crore,” officials said.

No comments:

Post a Comment